Scope of Work
- Identification and protection all rail infrastructure impacted by the delivery of the scope
- Possession planning for schedule weekend track outages
- Clearing of vegetation on the face and top of the crib wall
- Locally infilling the crib units with stabilised sand as required for installation of the soil nails
- Drilling and Installation of soil nails
- Installation of mesh/reinforcement, strip drains and weep hole drains
- Application of shotcrete
- Construction of drainage lines
Erskineville Stabilisation and Remediation Works