Client

Sydney Trains

Sector

Rail & Bridges

Location

Erskineville

Scope of Work
  • Identification and protection all rail infrastructure impacted by the delivery of the scope
  • Possession planning for schedule weekend track outages
  • Clearing of vegetation on the face and top of the crib wall
  • Locally infilling the crib units with stabilised sand as required for installation of the soil nails
  • Drilling and Installation of soil nails
  • Installation of mesh/reinforcement, strip drains and weep hole drains
  • Application of shotcrete
  • Construction of drainage lines

Erskineville Stabilisation and Remediation Works

Degnan are delivering stabilisation and remediation works to an existing crib wall at Erskineville for Sydney Trains. The works are being delivered in scheduled weekend track closures

Goulburn railway station is a heritage-listed railway station with state significance as one of the earliest principal rail locations in NSW. Its main station foundation stone was laid in May 1868 and the station opened in 1869.